Customer: Elbasa
Date: September 2015 – December 2015
Project location: Former facilities of ELBASA in Esparraguera (Barcelona)

Demolition of the pavilions using shears, management of debris and non-dangerous wastes in authorized managing plant

Turnkey Project for ELBASA.

After the request for the corresponding licenses and the payment of rates required by the town hall, the selective demolition of four pavilions that formed part of the ELBASA company was carried out. Due to acts of vandalism that took place, the cleaning of non-dangerous wastes was carried out previously and they were removed to the dump for destruction.

Once the pavilions were demolished, the reutilization of the clean debris for landfill of the present unevenness in the work was carried out.

 